S.No | Description | Quantity | Rate | Amount |
1 | Ground Floor |   |   |   |
2 | First Floor |   |   |   |
3 | Headroom |     |   |   |
  |   |   |   |   |
  |   |   |   |   |
  |   |   |   |   |
S.No | Details | Stage | Amount |
1 | Agreement Signing | 3% of Total Cost |   |
2 | Mobilization Advance | 17% of Total Cost |   |
3 | Basement Completed | 20% of Total Cost |   |
4 | Ground Floor Brick Work | 7.5% of Total Cost |   |
5 | Ground Floor Roof Completed | 15% of Total Cost |   |
6 | First Floor Brick Work | 7.5% of Total Cost |   | 7 | First Floor Roof Completed | 15% of Total Cost |   | 8 | Plastering Completed | 10% of Total Cost |   | 9 | Handover | 5% of Total Cost |   |
Employer | Details |