Civil Work

  • Depth of the Earth work excavation for foundations is according to the structural Design and Detailed drawing. (Excavation quantity may vary based on site condition, maximum 6 depth allowed)
  • Laying of P.C.C 1:4:8 using 40 mm metal laid in layers 75mm thick for foundations.
  • The height of the formed ground car parking level from the Road level is 1’6”
  • The height of the ground level from the Road level is 3’6” (Including finishing) or as allowed by the authorities
  • Width of the External Plinth Beam is 1’3”x0’9”
  • All Concrete 1:2:4 ratio Footing/Column/Beam and Roof Slab(RMC) (Cement: M Sand)
  • Back filling for the foundations using excavated earth would be well watered and consolidated (Msand quarry powder waste)
  • Basement brick work in CM 1:5 using quality Bricks for 230 mm thick above Plinth Beam.
  • External wall 9clay BRICK work (basic cost of brick INR 10.50/)--.
  • Internal partition wall 4.5 clay brick work (basic cost of brick INR10.50/)-.
  • Parapet Wall 4.5 Clay brick work 30 height (basic cost of brick INR10.50/)-
  • The clear floor height is 10 (including roof slab) to the bottom of the roof slab or as allowed by the authorities based on construction variations
  • The super structure Brick work up to lintel and roof should be completed on all aspects before concreting of each
  • Lintels- cut lintel as per architectural design
  • Sunshade 1 projected from the external
  • Inner and outer plastering thickness should not be more than 12mm" with normal finishes (Cement:P sand).
  • RCC surfaces plastering with CM 1:5 (Cement:M Sand).
  • Supply and fabrication of TMT ISI steel for all RCC works Fe550 Basic Cost Of Steel-INR70/-per kg. (GBR TMT/ARS TMT)
  • Cement used for construction specific Grade as per Structural Engineers recommendation. Cement Brand: FOR RCC WORK CORAMANTAL/ ZUARI Basic Cost Of Cement-INR380/-

Flooring

  • Depth of the Earth work excavation for foundations is according to the structural Design and Detailed drawing. (Excavation quantity may vary based on site condition, maximum 6 depth allowed)
  • Laying of P.C.C 1:4:8 using 40 mm metal laid in layers 75mm thick for foundations.
  • The height of the formed ground car parking level from the Road level is 1
  • The height of the ground level from the Road level is 3 (Including finishing) or as allowed by the authorities
  • Width of the External Plinth Beam is 10x09
  • All Concrete 1:2:4 ratio Footing/Column/Beam and Roof Slab(RMC) (Cement: M Sand)
  • Back filling for the foundations using excavated earth would be well watered and consolidated (msand quarry powder waste)
  • Basement brick work in CM 1:5 using quality Bricks for 230 mm thick above Plinth Beam.
  • External wall 9clay BRICK work (basic cost of brick INR 10.50/)--.
  • Internal partition wall 4.5 clay brick work (basic cost of brick INR10.50/)-.
  • Parapet Wall 4.5 Clay brick work 30 height (basic cost of brick INR10.50/)-
  • The clear floor height is 10 (including roof slab) to the bottom of the roof slab or as allowed by the authorities based on construction variations
  • The super structure Brick work up to lintel and roof should be completed on all aspects before concreting of each
  • Lintels- cut lintel as per architectural design
  • Sunshade 1 projected from the external
  • Inner and outer plastering thickness should not be more than 12mm" with normal finishes (Cement:P sand).
  • RCC surfaces plastering with CM 1:5 (Cement:M Sand).
  • Supply and fabrication of TMT ISI steel for all RCC works Fe550 Basic Cost Of Steel-INR70/-per kg. (GBR TMT/ARS TMT)
  • Cement used for construction specific Grade as per Structural Engineers recommendation. Cement Brand: FOR RCC WORK CORAMANTAL/ ZUARI Basic Cost Of Cement-INR380/-

Pest Control

    Main Door: (3;0;X 7;0;)1nos
    Anti termite treatment has to be carried out in following stages:
  • After Earth work Excavation for footing.
  • After basement filling (injection at every3 feet level) Treatment for wooden joineries

Doors

    Main Door: (3;0;X 7;0;)1nos
    • Main Door: Teak Wood frame with Teak Wood shutter(door inr14500/-) (Basic cost of frame INR5500/- Lock-2000/-)
    • Frame size:5;X 4
    • Fittings:Regular Fittings Brass Finish
    • 3 no of 5 Hinges for Main door shutters.
    • 8 at top and 6 at bottom Tower Bolt for Door shutters.
    • Any decorative beading not included for any wood work
    Room Door: (30X70)
    • Teak wood frame with readymade membrane  door 30mm thick (Basic cost of frame –inr3500/-, Shutter basic cost-inr2800/- ss antic finish lock-inr600/-)
    • Frame size: 4X 3
    • Fittings: Regular Fittings
    • 3 no of 5 Hinges for Main door shutters.
    • 8 at top and 6 at bottom Tower Bolt
    • Water Proof Pvc Door for toilet
    • Kitchen and Pooja door not included

V Windows

  • Frame :  4x2 thick wooden frame and 1 thickness windows shutter all 4 side 3 frame middle 3mm pined glass (master bedroom 2nos size (3x4), other bedroom -1nos size (3x4), / kitchen 1’nos size (3x3),  living 2nos size (4x4),, dining 1nos size (3x4),  all toilet 2’x2’ventilater with exhaust provision )
  • Fittings: Regular Fittings
  • Glass: 3mm Clear Glass.
  • Grills with 10mm square rods.

Staircase Handrail

  • SS Handrail 30 Height, Railing Made By SS 10mm Square bar. Top rail 1.5 SS Circular top railing. Cost included material labour and fixing (Basic cost 650/-per rft). 

Painting Work

  • Providing and painting two coats of Asian Tractor Emulsion paint over two coats of wall putty over one coat of wall primer for internal walls. for ceiling one coat primer two coat Asian Tractor Emulsion paint finish.
  • Providing and painting two coats of weather coat paint Asian ACE, over one coat of white cement for external wall,Bassage,Staircase and common area.
  • Providing and painting two coats of varnish Finish for Main door.
  • Enamel paint finish for grill and all other door frames.

Electrical

  • Concealed boxes:GI box
  • Wires:Orbit
  • Distribution board:Standard with door.
  • No.of distribution boards: One DB for building
  • MCB's & Isolators:ANGER/STD
  • Rotary Switch:Domestic Range
  • Switches:Star X/ Orbit/ Sleek
  • Fan regulator:Switch Type
  • Fan hook:G.I.
  • Bedrooms:2nos light point, 2nos 5amp Socket, 1nos fan point & 1nos AC point
  • Toilet:1nos Gyeser Point, 1nos light point , 1 nos exhaust point
  • Hall/Dining:4nos of light point, 2 fan point, 3nos of tv power socket.
  • Fan hook:2nos of 15amps socket, 2nos 5amp socket, 1nos of fan point, 2nos of light point,1nos RO point .

Plumbing

  • Inner Cold water Pipes CPVC (asirwath)
  • External Water line Pipe PVC
  • Inner Hot water pipes CPVC (asirwath)
  • Soil and waste water pipes PVC (Regular)
  • Plumbing Fittings: 2 in 1 wall Mixer (inr3000/-) & Head shower/rod (inr1000/-)– Parryware
  • Sink: KAG Single bowl SS Sink inr 2000/-  
  • EWC: Floor mounted Open tank – White colour – Parryware (ewc/tank inr3600/-)
  • Sink Tap: Long Body tap inr900/-
  • PVC traps: SS open door type.
  • Wash basin inr1100/- tap-inr400/- Parryware

Annexure II

Commercial Offer
  • Commercial Offer
  • Architectural Drawings: Floor Plan builder scope.
  • 1000ltr water tank pvc tank.
  • Staircase SS railing Included.
  • Floor plan and building front elevation view contractor scope.
Important Note:
  • GST not added in above price. Client Require GST invoice means 18% GST added Extra.
  • Any other bribes for local body client scope.
  • Roof area will be consider as billing construction area.
  • If any additional changes or correction client side amount will be chargeable.
  • Power, Water will be client scope
  • From the day of stage completion within 15days payment has to be released for next stage.
Exclusive
  • Elevation Tiles, wood and granite not included.
  • Weathering Coarse/Weathering Tile Not included.
  • Approval and EB connection cost not included.
  • Motor, Sump, Septic tank and compound wall not included.
  • Safety grill for doors not included.
  • False ceiling, wardrobe, landscapr, paver maingate, wicket gate related piller and showcase any other wood works not included.
  • Soil test.
  • Structural design (SOMADEV NAGESH Consulting Engineer)

Annexure III

S.No Description Quantity Rate Amount
1 Ground Floor      
2 First Floor      
3 Headroom        
         
         
         
(Cost only for building construction area)
S.No Details Stage Amount
1 Agreement Signing 3% of Total Cost  
2 Mobilization Advance 17% of Total Cost  
3 Basement Completed 20% of Total Cost  
4 Ground Floor Brick Work 7.5% of Total Cost  
5 Ground Floor Roof Completed 15% of Total Cost  
6 First Floor Brick Work 7.5% of Total Cost  
7 First Floor Roof Completed 15% of Total Cost  
8 Plastering Completed 10% of Total Cost  
9 Handover 5% of Total Cost  