Civil Work

  • Depth of the Earth work excavation for foundations is according to the structural Design and Detailed drawing. (Excavation quantity may vary based on site condition, maximum 70depth allowed)
  • Laying of P.C.C 1:4:8 using 40 mm metal laid in layers 75mm thick for foundations.
  • The height of the formed ground car parking level from the Road level is 26
  • The height of the ground level from the Road level is 40(Including finishing) or as allowed by the authorities
  • Width of the External Plinth Beam is 16x09
  • All Concrete 1:1.5:3 ratio Footing/Column/Beam and Roof Slab(RMC)(Cement: M Sand)
  • Back filling for the foundations using excavated earth would be well watered and consolidated (msand quarry powder waste)
  • Basement brick work in CM 1:5 using quality Bricks for 230 mm thick above Plinth Beam.
  • External wall 9clay WIRE CUT BRICK work (basic cost of brick INR 11.50/)--.
  • Internal partition wall 4.5WIRE CUT BRICK work (basic cost of brick INR11.50/)-.
  • Parapet Wall 4.5Clay WIRE CUT BRICK 30 height (basic cost of brick INR11.50/)-
  • The clear floor height is 110(including roof slab) to the bottom of the roof slab or as allowed by the authorities based on construction variations
  • The super structure Brick work up to lintel and roof should be completed on all aspects before concreting of each state.
  • Lintels- cut lintel as per architectural design
  • Sunshade 16projected from the external walls.
  • Inner and outer plastering thickness should not be more than 12mm with normal finishes (Cement: River sand).
  • RCC surfaces plastering with CM 1:5 (Cement: River sand).
  • Supply and fabrication of TMT ISI steel for all RCC works Fe550 Basic Cost Of Steel-INR93/-per kg.(TATA STEEL/JSW STEEL)
  • Cement used for construction–specific Grade as per Structural Engineers recommendation. Cement Brand: FOR RCC WORK CORAMANTAL/ULTRATECH Basic Cost Of Cement-INR420/-

Flooring

  • Supply and laying of flooring with Granite flooring 15mm thick @ INR100/- sq.ft over mortar bed in CM 1:8 including pointing and finishing for ground floor and first floor.
  • Toilet floor tiles 20x20 Basic cost INR70/- Toilet wall tiles basic cost of tiles INR 85/- upto 70 height all side
  • Supply and laying of Path area @ Rs110/- per sq.ft * over mortar bed in 1:8 including pointing and finishing, staircase, landing
  • Kitchen Granite 150 Maximum length allowed, Kitchen Wall tiles 40 height over the counter. basic cost of Granite INR70/-

Pest Control

    Anti termite treatment has to be carried out in following stages:
  • After Earth work Excavation for footing.
  • After basement filling (injection at every 3 feet level) Treatment for wooden joineries.

Doors

    Main Door: (6'0”X 7'0”) 1nos
    • Main Door: Teak Wood frame with Teak Wood shutter(door inr14500/-) (Basic cost of frame INR10000/- Lock-5000/-)
    • Frame size: 5X 4
    • Fittings: Regular Fittings Brass Finish
    • 3 no of 5 Hinges for Main door shutters.
    • 8 at top and 6 at bottom Tower Bolt for Door shutters.
    • Any decorative beading not included for any wood work
    Room Door: (3'0”X 7'0”)
    • Teak wood frame with wooden door 30mm thick (Basic cost of frame -inr4500/-, Shutter basic cost-inr7000/- ss antic finish lock-inr1500/-)
    • Frame size: 4X 3
    • Fittings: Regular Fittings
    • 3 no of 5 Hinges for Main door shutters.
    • 8 at top and 6 at bottom Tower Bolt
    • Water Proof WPC Door for toilet
    • Kitchen and Pooja door not included

V Windows

  • Frame : 4x2 thick wooden frame and 1 thickness windows shutter all 4 side 3 frame middle 3mm pined glass (master bedroom 2nos size (3x4), other bedroom -2nos size (3x4), / kitchen 2nos size (3x3),living 2nos size (4x4),, dining 2nos size (3x4),  all toilet 2x2ventilater with exhaust provision)
  • Fittings: Regular Fittings
  • Glass: 5mm Clear Glass.
  • Grills with 12mm square rods.

Staircase Handrail

  • SS Handrail 30 Height with glass, Railing Made By SS 10mm Square bar. Top rail 1.5 SS Circular top railing. Cost included material labour and fixing (Basic cost 1500/-per rft).

Painting Work

  • Providing and painting two coats of Asian Royel Emulsion paint over two coats of wall putty over one coat of wall primer for internal walls. for ceiling Putty one coat primer two coat Asian Royel Emulsion paint finish.
  • Providing and painting two coats of weather coat paint Asian ULTIMA, over one coat of white cement for external wall, Passage, Staircase and common area.
  • Providing and painting two coats of varnish Finish for Main door.
  • Enamel paint finish for grill and all other door frames.

Electrical

  • Concealed boxes:GI box
  • Wires:Polycop/Finolex
  • Distribution board:Standard with door.
  • No.of distribution boards: One DB for building
  • MCB's & Isolators:ANGER/STD
  • Rotary Switch:Domestic Range
  • Switches:Anger
  • Fan regulator:Switch Type
  • Fan hook:G.I.
  • Living/dining and master bedroom spot light included
  • Bedrooms:2nos light point, 2nos 5amp Socket, 1nos fan point & 1nos AC point
  • Toilet:1nos Gyeser Point, 1nos light point , 1 nos exhaust point
  • Hall/Dining:4nos of light point, 2 fan point, 3nos of tv power socket.
  • Kitchen:2nos of 15amps socket, 2nos 5amp socket, 1nos of fan point, 2nos of light point,1nos RO point.

Plumbing

  • Inner Cold water Pipes CPVC (asirwath)
  • External Water line Pipe PVC (star/supreme)
  • Inner Hot water pipes CPVC (asirwath)
  • Soil and waste water pipes PVC (Regular)
  • Plumbing Fittings: single liver diverter (inr7500/-) & Head shower/rod (inr3500/-)– Parryware /jaguar
  • Hand shower for master bedroom Inr3000/-
  • Sink: KAG double bowl SS Sink inr 10000/-  
  • EWC: Floor mounted Open tank – White colour – Parryware (ewc/tank inr10000/-)
  • EWC: master bedroom concealed tank with wall mounted ewc inr(20000/-)
  • Sink Tap: Long Body tap inr2500/-
  • PVC traps: SS open door type.
  • Wash basin inr3000/- tap-inr1500/- ---Parryware

Annexure II

Commercial Offer
  • Architectural Drawings: Floor Plan builder scope.
  • 2000ltr water tank brick work tank.
  • Staircase SS railing Included.
  • Floor plan and building front elevation view contractor scope.
  • Soil test.
  • Structural design (SOMADEV NAGESHConsulting Engineer)
  • Wardrobe/living dining master bedroom false ceiling
  • Front compound wall and main gate (inr40000/-)
Important Note:
  • GST not added in above price. Client Require GST invoice means 18% GST added Extra.
  • Any other bribes for local body client scope.
  • Roof area will be consider as billing construction area.
  • If any additional changes or correction client side amount will be chargeable.
  • Power, Water will be client scope
  • From the day of stage completion within 15days payment has to be released for next stage.
Exclusive
  • Elevation Tiles, wood and granite not included.
  • Weathering Coarse/Weathering Tile Not included.
  • Approval and EB connection cost not included.
  • Motor, Sump, Septic tank and compound wall not included.
  • Safety grill for doors not included.
  • landscapr, paver maingate, wicket gate related piller and showcase any other wood works not included.
  • Pile foundation difference cost

Annexure III

S.No Description Quantity Rate Amount
1 Ground Floor      
2 First Floor      
3 Headroom        
         
         
         
(Cost only for building construction area)
S.No Details Stage Amount
1 Agreement Signing 3% of Total Cost  
2 Mobilization Advance 17% of Total Cost  
3 Basement Completed 20% of Total Cost  
4 Ground Floor Brick Work 7.5% of Total Cost  
5 Ground Floor Roof Completed 15% of Total Cost  
6 First Floor Brick Work 7.5% of Total Cost  
7 First Floor Roof Completed 15% of Total Cost  
8 Plastering Completed 10% of Total Cost  
9 Handover 5% of Total Cost  
Employer Contractor